Question

1 Approved Answer

The following table lists the tasks, the expected activity times, and preceding tasks for a project. Preceding Task Task Length None 5 A 3 None

image text in transcribed
The following table lists the tasks, the expected activity times, and preceding tasks for a project. Preceding Task Task Length None 5 A 3 None 2 A, C 5 B, D 2 E 4 F 6 1. Draw the project network diagram. Be sure to include the START and END nodes and arrows between activities. 2. List the activities on the Critical Path? 3. Which activities have slack and how much? 4. In order to speed up the project, Ethan recommends paying overtime to reduce the time for activity B. Sean recommends hiring temp staff to speed up activity D. Do you agree with Ethan or Sean? Why or why not? Use a full size clean white 8.5x11 sheet of paper and hand draw a NEAT and ORGANIZED project network diagram. Neatly add ES, EF, LS, and LF to each node. I recommend using multiple colored pens/pencils. Neatly ANSWER questions 2, 3, and 4 on the same paper below the diagram. Either scan or take a picture of your page and upload it for this

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management Awareness And Change

Authors: Frank Martin , John Thompson , Jonathan M.Scott

8th Edition

1473726336, 978-1473726338

More Books

Students also viewed these General Management questions