The following table of probabilistic time estimates ( in weeks ) and activity predecessors are provided for a project. Activity optimistic time most likely time

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
Activity
optimistic
time
most likely
time
pessimistic
time
Activity Predecessor
A
3
5
7
--
B
4
8
10
A
C
2
3
5
A
D
6
9
12
B, C
E
5
9
15
D
Table 1
Reference: Ref 1
Using Table 1, the variance for activity E is
A.2.582.
B.2.778.
C.1.667.
D.1.291.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: Jay Heizer, Barry Render

11th edition

9780132921145, 132921146, 978-0133408010

More Books

Students also viewed these General Management questions