The following table represents a plan for a project: Job No. Predecessor Job(s) Most Optimistic (days) Most Likely (days) Most Pessimistic (days) 1 -- 2

The following table represents a plan for a project:

Job No. Predecessor Job(s) Most Optimistic (days) Most Likely (days) Most Pessimistic (days)
1 -- 2 3 4
2 1 1 2 3
3 1 4 5 12
4 1 3 4 11
5 2 1 3 5
6 3 1 2 3
7 4 1 8 9
8 5, 6 2 4 6
9 8 2 4 12
10 7 3 4 5
11 9, 10 5 7 8

What is the expected completion time for the project and what is the probability that the project will take morethan 30 days to complete?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Effective small business management An Entrepreneurial Approach

Authors: Norman M. Scarborough

10th Edition

132157462, 978-0132157469

More Books

Students also viewed these General Management questions