The following table shows a WBS with 11 tasks. Note that each task has an ID, a description, duration, and a reference to predecessor tasks,
The following table shows a WBS with 11 tasks. Note that each task has an ID, a description, duration, and a reference to predecessor tasks, if any, which must be completed before the task can begin. Construct a PERT/CPM chart from these tasks (similar to chart in Slide 20 Ch 3). Also, identify the critical path for this project (what are the tasks on the critical path and how long would it take?).
Task No. | Description | Duration (Days) | Predecessor Tasks |
1 | Develop Plan | 1 | - |
2 | Assign Tasks | 4 | 1 |
3 | Obtain Hardware | 17 | 1 |
4 | Programming | 60 | 2 |
5 | Install Hardware | 10 | 3 |
6 | Program Test | 25 | 4 |
7 | Write User Manual | 25 | 5 |
8 | Concert Files | 15 | 5 |
9 | System Test | 25 | 6 |
10 | User Training | 20 | 7,8 |
11 | User Test | 25 | 9,10 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started