The following table shows estimates of activity times (weeks) for a project: suppose that the critical path is A-C-E-F-G. What is the probability that the
The following table shows estimates of activity times (weeks) for a project: suppose that the critical path is A-C-E-F-G. What is the probability that the project will be completed
a. within 33 weeks?
b. within 30 weeks?
c. within 35 weeks?
d. in more than 32 weeks?
Activity | Optimistic TIme | Most probable time | Pessimisitic Time |
A | 4 | 5 | 6 |
B | 2.5 | 3 | 3.5 |
C | 6 | 7 | 8 |
D | 5 | 5.5 | 9 |
E | 6 | 7 | 8 |
F | 1 | 3 | 5 |
G | 8 | 10 | 12 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started