Question

1 Approved Answer

The following table shows estimates of activity times (weeks) for a project: suppose that the critical path is A-C-E-F-G. What is the probability that the

The following table shows estimates of activity times (weeks) for a project: suppose that the critical path is A-C-E-F-G. What is the probability that the project will be completed

a. within 33 weeks?

b. within 30 weeks?

c. within 35 weeks?

d. in more than 32 weeks?

Activity Optimistic TIme Most probable time Pessimisitic Time
A 4 5 6
B 2.5 3 3.5
C 6 7 8
D 5 5.5 9
E 6 7 8
F 1 3 5
G 8 10 12

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

The New Microfinance Handbook A Financial Market System Perspective

Authors: Joanna Ledgerwood, Julie Earne, Candace Nelson

1st Edition

0821389270, 978-0821389270

More Books

Students also viewed these Finance questions

Question

1. Does your voice project confidence? Authority?

Answered: 1 week ago