Question
The following table shows the information on a marketing project .It is currently at the end of day 48. Determine if the project is in
- The following table shows the information on a marketing project .It is currently at the end of day 48.
- Determine if the project is in control based on time and cost to date.
- If not, what is the cost of over age or underage?
Can you please explain the math step by step
Activity | Duration | Budget | ActualCost | % Complete |
1-2 | 10 | 300 | 250 | 100.00 |
2-3 | 8 | 400 | 450 | 100.00 |
2-4 | 12 | 350 | 380 | 100.00 |
3-5 | 18 | 405 | 400 | 70.00 |
5-6 | 16 | 450 | ------- | 0.00 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Management Science The Art Of Modeling With Spreadsheets
Authors: Stephen G. Powell, Kenneth R. Baker
4th Edition
978-1118517376, 9781118800348, 1118517377, 1118800346, 978-1118582695
Students also viewed these General Management questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App