The following tasks are to be performed on an assembly line: TASK SECONDS TASKS THAT MUST PRECEDE A 3 0 B 1 6 A C

The following tasks are to be performed on an assembly line:
TASK SECONDS TASKS THAT MUST PRECEDE
A 30
B 16 A
C 21 B
D 15 B
E 17 C
F 14 D
G 20 E, F
H 9 G
The workday is 8 hours long. The demand for completed product is 900 per day.
Find the cycle time required to meet the desired output rate.
Note: Round your answer to 1 decimal place.
What is the theoretical number of workstations required to meet the desired output rate?
Note: Round up your answer to the next whole number.
Balance the line using sequential restrictions and the longest-operating-time rule. Determine the task under each workstation and the idle time for each such task.
Note: Leave no cells blank - be certain to enter "0" wherever required. Round your answers to 1 decimal place.
What is the efficiency of the line balanced as in part (d) assuming it is running at the cycle time determined in part (a)?
Note: Round your answer to 1 decimal place.
Suppose that demand rose from 900 to 1,000 units per day. Determine the cycle time. Use the solution obtained in part (d).)
Note: Round your answer for cycle time down to the nearest whole number.
Suppose that demand rose from 900 to 1,400 units per day. Determine the cycle time. (Use the solution obtained in part (d).)
Note: Round your answer for cycle time down to the nearest whole number.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Supply Chain Management A Logistics Perspective

Authors: John coyle, John Langley, Robert Novack, Brain Gibson

9th edition

9780538479189, 9781285400945, 538479191, 538479183, 1285400941, 978-0538479196

More Books

Students also viewed these General Management questions