The following tasks are to be performed on an assembly line: TASK SECONDS TASKS THAT MUST PRECEDE A 2 5 B 2 0 A C

The following tasks are to be performed on an assembly line:
TASK SECONDS TASKS THAT MUST PRECEDE
A 25
B 20 A
C 16 B
D 35 B
E 27 C
F 15 D
G 10 E, F
H 35 G
The workday is 8.75 hours long. The demand for completed product is 700 per day. What is the theoretical number of workstations required to meet the desired output rate?
Note: Round up your answer to the next whole number.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Retailing Management

Authors: Michael Levy, Barton A Weitz

8th Edition

0073530026, 9780073530024

More Books

Students also viewed these General Management questions