Question
1 Approved Answer
The following time-phasing chart is available for a single item within an MRP system. Complete this chart by estimating inventory on hand and planned order
- The following time-phasing chart is available for a single item within an MRP system. Complete this chart by estimating inventory on hand and planned order release values. Lead time is 2 weeks, and order policy is 100 units, which means this part can be ordered only in 100-unit batches. Inventory replenishment is JIT; lead times are negligible.