Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

The following work packages are determined for a commercial project: Work Package Duration (months) Relationship Total budgeted cost Mobilization 1 $200,000 Earthwork 3 Mobilization $500,000

image text in transcribed
image text in transcribed
The following work packages are determined for a commercial project: Work Package Duration (months) Relationship Total budgeted cost Mobilization 1 $200,000 Earthwork 3 Mobilization $500,000 Site utilities 3 SS and FF with $250,000 earthwork Foundation and 5 FS with Mobilization $750,000 substructure Superstructure and shell 3 FS with foundation $1,500,000 and substructure Parking lot and 2 SS/1 with $350,000 landscaping superstructure Deliverables: 1. Cost loaded Gantt chart. Assume cost is uniformly distributed 2. Cash outflow curve (S-curve) 3. Cash inflow curve. The following contract provisions must be considered: a. Pay applications are prepared and submitted at the end of each month. b. Progress payment are received one month after your application is submitted, c. The owner retains 10% of each progress payment. The retainage value will be paid in full 2 month after project completion 4. Overdraft profile showing the maximum overdraft and profit (8%) The following work packages are determined for a commercial project: Work Package Duration (months) Relationship Total budgeted cost Mobilization 1 $200,000 Earthwork 3 Mobilization $500,000 Site utilities 3 SS and FF with $250,000 earthwork Foundation and FS with Mobilization $750,000 substructure Superstructure and shell 3 FS with foundation $1,500,000 and substructure Parking lot and SS/1 with $350,000 landscaping superstructure 5 N Deliverables: 1. Cost loaded Gantt chart. Assume cost is uniformly distributed 2. Cash outflow curve (S-curve). 3. Cash inflow curve. The following contract provisions must be considered: a. Pay applications are prepared and submitted at the end of each month. b. Progress payment are received one month after your application is submitted. c. The owner retains 10% of each progress payment. The retainage value will be paid in full 2 month after project completion. 4. Overdraft profile showing the maximum overdraft and profit (8%). The following work packages are determined for a commercial project: Work Package Duration (months) Relationship Total budgeted cost Mobilization 1 $200,000 Earthwork 3 Mobilization $500,000 Site utilities 3 SS and FF with $250,000 earthwork Foundation and 5 FS with Mobilization $750,000 substructure Superstructure and shell 3 FS with foundation $1,500,000 and substructure Parking lot and 2 SS/1 with $350,000 landscaping superstructure Deliverables: 1. Cost loaded Gantt chart. Assume cost is uniformly distributed 2. Cash outflow curve (S-curve) 3. Cash inflow curve. The following contract provisions must be considered: a. Pay applications are prepared and submitted at the end of each month. b. Progress payment are received one month after your application is submitted, c. The owner retains 10% of each progress payment. The retainage value will be paid in full 2 month after project completion 4. Overdraft profile showing the maximum overdraft and profit (8%) The following work packages are determined for a commercial project: Work Package Duration (months) Relationship Total budgeted cost Mobilization 1 $200,000 Earthwork 3 Mobilization $500,000 Site utilities 3 SS and FF with $250,000 earthwork Foundation and FS with Mobilization $750,000 substructure Superstructure and shell 3 FS with foundation $1,500,000 and substructure Parking lot and SS/1 with $350,000 landscaping superstructure 5 N Deliverables: 1. Cost loaded Gantt chart. Assume cost is uniformly distributed 2. Cash outflow curve (S-curve). 3. Cash inflow curve. The following contract provisions must be considered: a. Pay applications are prepared and submitted at the end of each month. b. Progress payment are received one month after your application is submitted. c. The owner retains 10% of each progress payment. The retainage value will be paid in full 2 month after project completion. 4. Overdraft profile showing the maximum overdraft and profit (8%)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Value Investing

Authors: Mike Hartley

1st Edition

979-8864443309

More Books

Students also viewed these Finance questions

Question

Describe the factors influencing of performance appraisal.

Answered: 1 week ago

Question

What is quality of work life ?

Answered: 1 week ago