The Freddy Construction Corporation (MCC) signed a $15 million contract in late 20x0 to build a road. Data on the contract is as follows: 20x1
The Freddy Construction Corporation (MCC) signed a $15 million contract in late 20x0 to build
a road. Data on the contract is as follows:
20x1 20x2 20x3 20x4
Costs incurred during year $3,000,000 $6,500,000 $4,000,000 $3,200,000
Expected costs to complete 9,000,000 5,000,000 3,100,000 -
Billings 7,500,000 - - 7,500,000
Required
For each of the parts below, prepare the mini income statement for the project for each year and
calculate the net investment of the project that will be shown on the balance sheet at the end of
each year.
a. Freddy uses an input based approach to calculating the percentage of completion.
b. Freddy uses an output based approach to calculating the percentage of completion and
has calculated the percentages of completion as follows:
20x1 20%
20x2 65%
20x3 85%
20x4 100%
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started