the fundamentals of production planning and control 4. Product A is made from two components, Band C. It takes one B and three Cs to

the fundamentals of production planning and control

4. Product A is made from two components, Band C. It takes one B and three Cs to make a single product A. Component B is made from two part Ds. Component C is made from one part D and 2 part Cs. Use this information together with the data below to answer the following questions:

part lead time Lot Size On-Hand Scheduled Recpts
B 1 Lot-for-Lot 10 none
C 2 200 100 none
D 1 300 120 none
E 2 500 0 500, week 1

a. Make MRP records for B, C, D, and E. Production quantities and production start dates for A are: 20 in week 2, 50 in week 4, 30 in week 6,40 in week 7, 50 in week 9, and 40 in week 11. b. Suppose the quality manager told you the 120 part Ds on hand were damaged in a sprinkler accident and not available for production. What actions should you take? c. The purchasing manager has just informed you that the supplier for part E was only able to ship 480 of the 500 you are scheduled to receive in week 1. What potential problems would this mean and how would you deal with it?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions