the fundamentals of production planning and control 4. Product A is made from two components, Band C. It takes one B and three Cs to
the fundamentals of production planning and control
4. Product A is made from two components, Band C. It takes one B and three Cs to make a single product A. Component B is made from two part Ds. Component C is made from one part D and 2 part Cs. Use this information together with the data below to answer the following questions:
part | lead time | Lot Size | On-Hand | Scheduled Recpts |
B | 1 | Lot-for-Lot | 10 | none |
C | 2 | 200 | 100 | none |
D | 1 | 300 | 120 | none |
E | 2 | 500 | 0 | 500, week 1 |
a. Make MRP records for B, C, D, and E. Production quantities and production start dates for A are: 20 in week 2, 50 in week 4, 30 in week 6,40 in week 7, 50 in week 9, and 40 in week 11. b. Suppose the quality manager told you the 120 part Ds on hand were damaged in a sprinkler accident and not available for production. What actions should you take? c. The purchasing manager has just informed you that the supplier for part E was only able to ship 480 of the 500 you are scheduled to receive in week 1. What potential problems would this mean and how would you deal with it?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started