The government facilities manager was not on site as planned to sign for critical contract materials, so they were returned to the shipper. As a
The government facilities manager was not on site as planned to sign for critical contract materials, so they were returned to the shipper. As a result, the materials were delivered two weeks late, which forced an equal extension to the contract schedule. Which type of change does this represent?
Step by Step Solution
★★★★★
3.48 Rating (155 Votes )
There are 3 Steps involved in it
Step: 1
The situation you described represents a compensatory change in the context of pr...