Question
1 Approved Answer
The Government's current estimate at completion (EAC) including estimated contractor profit is $80.4 million. The program is budgeted for $80.9 million. What can the program
The Government's current estimate at completion (EAC) including estimated contractor profit is $80.4 million. The program is budgeted for $80.9 million. What can the program manager (PM) conclude based on this information?
The program has excess funding that should be returned.
The program has sufficient funding and will achieve cost objectives.
The program will not achieve cost objectives and will run out of funding.
The program currently has sufficient funding to achieve cost objectives, but should be closely monitored for any changes.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started