Question

1 Approved Answer

The Government's current estimate at completion (EAC) including estimated contractor profit is $80.4 million. The program is budgeted for $80.9 million. What can the program

The Government's current estimate at completion (EAC) including estimated contractor profit is $80.4 million. The program is budgeted for $80.9 million. What can the program manager (PM) conclude based on this information?

The program has excess funding that should be returned.

The program has sufficient funding and will achieve cost objectives.

The program will not achieve cost objectives and will run out of funding.

The program currently has sufficient funding to achieve cost objectives, but should be closely monitored for any changes.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Foundations In Personal Finance

Authors: Dave Ramsey

3rd Edition

1936948524, 978-1936948529

Students also viewed these Finance questions

Question

a sin(2x) x Let f(x)=2x+1 In(be)

Answered: 1 week ago