Question
1 Approved Answer
The highest element in the hierarchical breakdown of the Work Breakdown Structure (WBS) is The project Sub deliverables A work package Major deliverables
The highest element in the hierarchical breakdown of the Work Breakdown Structure
(WBS) is
- The project
- Sub deliverables
- A work package
- Major deliverables