The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the
The IRR evaluation method assumes that cash flows from the project are reinvested at the same rate equal to the IRR. However, in reality the reinvested cash flows may not necessarily generate a return equal to the IRR. Thus, the modified IRR approach makes a more reasonable assumption other than the projects IRR.
Consider the following situation:
Celestial Crane Cosmetics is analyzing a project that requires an initial investment of $2,750,000. The projects expected cash flows are:
Year | Cash Flow |
---|---|
Year 1 | $325,000 |
Year 2 | 100,000 |
Year 3 | 425,000 |
Year 4 | 400,000 |
Celestial Crane Cosmeticss WACC is 10%, and the project has the same risk as the firms average project. Calculate this projects modified internal rate of return (MIRR):
23.33%
17.78%
-17.69%
18.89%
Step by Step Solution
There are 3 Steps involved in it
Step: 1
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started