Question

1 Approved Answer

The labor quantity variance is calculated by taking the actual hours times the standard rate minus the standard hours times the standard rate. Bateh Company

The labor quantity variance is calculated by taking the actual hours times the standard rate minus the standard hours times the standard rate. Bateh Company produces hot sauce. The following information is provided concerning its standard cost system for the year: Standard Data Actual Data Material 1/8 lb. @ $7.50 per lb. Produced 4,400 Labor 24 mins. @ $12 per hr. Materials cost $7.40 per pound Budgeted fixed overhead $28,350 Materials used 556 pounds Budgeted variable overhead $4.50 per unit Labor worked 1,610 hours totaling $19,481 Budgeted production 4,500 Actual overhead Fixed $20,000; Variable $28,400 How much is the labor quantity variance? answer

A) $161U.

B) $1,800F.

C). $1,639F.

D). $176U.

I know the answer is not A or C because I have submitted the answer twice. Please kindly help show the steps.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Software Licence Compliance Survive The Audits

Authors: R. Concessao

1st Edition

1539161560, 978-1539161561

More Books

Students also viewed these Accounting questions

Question

List four contaminations of a criterion.

Answered: 1 week ago

Question

8. Describe how cultural spaces are formed.

Answered: 1 week ago