The Laurenster Corporation is getting into the con-struction business. A list of activities and their optimistic, most likely, and pessimistic completion times are given in

The Laurenster Corporation is getting into the con-struction business. A list of activities and their optimistic, most likely, and pessimistic completion times are given in the following table for the next construction project.

DAYS ACTIVITY A B C D E F G H I J K a 3 2 1 6 2 6 1 3 10 14 2 m 6 4 2 7 4 10 2 6 11 16 8 b 9 6 3 8 6 14 6 9 12 21 11 IMMEDIATE PREDECESSORS C B, D A, E A, E F G G H, I

(a) Develop a project network for this problem. (b) Determine the expected duration and variance for each activity. (c) Determine the ES, EF, LS, LF, and slack time for each activity. Also determine the total proj-ect completion time and critical path(s). (d) What is the probability that this job will finish in 38 days or less?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Algebra advanced algebra with financial applications

Authors: Robert K. Gerver

1st edition

978-1285444857, 128544485X, 978-0357229101, 035722910X, 978-0538449670

More Books

Students also viewed these Mathematics questions