The layout redesign of the pediatric ward is expected to take 47 weeks. The standard deviation of the critical path is 2.17 weeks. Find the
The layout redesign of the pediatric ward is expected to take 47 weeks. The standard deviation of the critical path is 2.17 weeks. Find the z-value and determine the probabilities that the project will be completed within 50 weeks