The layout redesign of the pediatric ward is expected to take 47 weeks. The standard deviation of the path is 2.17 weeks. Find the Z-
The layout redesign of the pediatric ward is expected to take 47 weeks. The standard deviation of the path is 2.17 weeks. Find the Z- value and determine the probabilities that:
A. the project will be completed within 50 weeks
B. the project will take 49 weeks or longer.