The length of time expected to complete an activity assuming that its development proceeds normally is called the: Select one: a . Optimistic duration. b

The length of time expected to complete an activity assuming that its development proceeds normally is called the:
Select one:
a.
Optimistic duration.
b.
Most likely duration.
c.
Normal duration.
d.
Pessimistic duration.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Time Management

Authors: Patrick Forsyth

2nd Edition

0749460377, 978-0749460372

More Books

Students also viewed these General Management questions