The length of time expected to complete an activity assuming that its development proceeds normally is called the: Select one: a . Pessimistic duration. b

The length of time expected to complete an activity assuming that its development proceeds normally is called the:
Select one:
a.
Pessimistic duration.
b.
Normal duration.
c.
Optimistic duration.
d.
Most likely duration.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Time Management

Authors: Patrick Forsyth

4th Edition

0749475811, 978-0749475819

More Books

Students also viewed these General Management questions

Question

d. What language(s) did they speak?

Answered: 1 week ago