The Macon Company uses the high-low method to determine its cost equation. The following information was gathered for the past year: Machine Hours Direct Labor

The Macon Company uses the high-low method to determine its cost equation. The following information was gathered for the past year:

Machine Hours Direct Labor Costs
Busiest month (June) 21,500 $ 261,950
Slowest month (December) 15,000 $ 195,000

If Macon expects to use 17,500 machine hours next month, what are the estimated direct labor costs?

Multiple Choice

$220,750.

$180,250.

$203,250.

$235,500.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

International Project Finance

Authors: Felix I. Lessambo

1st Edition

3030963896, 978-3030963897

More Books

Students also viewed these Finance questions

Question

Q.No.1 Explain Large scale map ? Q.No.2 Explain small scale map ?

Answered: 1 week ago

Question

1. Signs and symbols of the map Briefly by box ?

Answered: 1 week ago