The maintenance department of an Oil and Gas Company has 6 large drilling equipment waiting for repairs. These are labelled A, B, C, D, E

The maintenance department of an Oil and Gas Company has 6 large drilling equipment waiting for repairs. These are labelled A, B, C, D, E and F. The respective repair times (in days) and the remaining days before the due date are given in the table below.


Equipment Time required Due (at the end of) day
A 1 30
B 8 27
C 3 38
D 27 57
E 2 29
F 29 42

[15 Marks]

  1. What will be the job sequences using (1) CR and (2) SPT rules?
  2. What will be the (1) average flow time, (2) average days late, and 3) average work in progress for the CR and SPT sequences?
  3. Apply the appropriate method to determine the sequence which will minimize the total number of late jobs.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Management

Authors: Robbins, DeCenzo, Coulter

7th Edition

132996855, 0-13-610982-9 , 9780132996853, 978-0-13-61098, 978-0136109822

More Books

Students also viewed these General Management questions

Question

Who is the Threat Notification Officer for the department?

Answered: 1 week ago