Question

1 Approved Answer

the maker of the world famous chocolate chip cookies needs to design a product layout for a new product, mint chocolate chip. the company plans

the maker of the world famous chocolate chip cookies needs to design a product layout for a new product, mint chocolate chip. the company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. the following table describes the tasks involved in the production of a mint chocolate chip cookie.

task = u, v, w, x, y, z

Immediate predecessor = none, u, v, v, w, x, y(respectively)

time(secs)= 4, 14, 12, 10, 6, 8

a. without considering projected demands , what is the minimum possible cycle time for this production line?

b. for output to equal projected demand, what should be the actual cycle time for this production line?

c. for output to equal projected demand, what is the minimum number of workstation needed?

d. for output to equal projected demand, what will be the percentage of idle time of the production line that uses the minimum number of workstations?

e. for output equal projected demand, what will be the first task performed at the last workstation of the production line uses the minimum number of stations?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Auditing A Practical Approach

Authors: Robyn Moroney, Fiona Campbell, Jane Hamilton

4th Edition

0730382648, 978-0730382645

More Books

Students also viewed these Accounting questions

Question

1. Discuss the four components of language.

Answered: 1 week ago