The manager of a local youth sports organization is planning its soccer season. The activities, their immediate predecessors, and the activity time estimates ( in
The manager of a local youth sports organization is planning its soccer season. The activities, their
immediate predecessors, and the activity time estimates in weeks are as follows.
Time weeks
Activity Description Predecessors Optim. Most Likely Pessim.
A Meet with board
B Interviewhire coaches A
C Reserve fields A
D Create schedule B C
E Meet with coaches B
F Register players A
G Order kits D
H Collect fees G
I Organize first practice E F H
a Draw the project network diagram.
b Compute the mean and variance of the duration of each activity. You may do this by hand or
by using technology, such as Excel.
c Determine the critical path, the expected project completion time, and the variance of the
project completion time.
d What is the probability that the planning process is completed within weeks?
e What is the probability that the planning process takes longer than weeks to complete?
f If the manager wants a probability of completing the planning process on time, how far
ahead of the first practice should they start working?
MS Panda Problem Set #Fall
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started