The manager of a local youth sports organization is planning its soccer season. The activities, their immediate predecessors, and the activity time estimates ( in

The manager of a local youth sports organization is planning its soccer season. The activities, their
immediate predecessors, and the activity time estimates (in weeks) are as follows.
Time (weeks)
Activity Description Predecessor(s) Optim. Most Likely Pessim.
A Meet with board 1.01.52.0
B Interview/hire coaches A 3.04.06.0
C Reserve fields A 2.03.05.0
D Create schedule B, C 1.52.02.5
E Meet with coaches B 2.03.04.0
F Register players A 1.02.04.0
G Order kits D 1.02.03.0
H Collect fees G 1.02.03.0
I Organize first practice E, F, H 0.51.02.0
(a) Draw the project network diagram.
(b) Compute the mean and variance of the duration of each activity. You may do this by hand or
by using technology, such as Excel.
(c) Determine the critical path, the expected project completion time, and the variance of the
project completion time.
(d) What is the probability that the planning process is completed within 12.1 weeks?
(e) What is the probability that the planning process takes longer than 14.2 weeks to complete?
(f) If the manager wants a 94.5% probability of completing the planning process on time, how far
ahead of the first practice should they start working?
MS 3053(Panda) Problem Set #10(Fall 2023)1

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles Of General Management

Authors: John L.Colley Jr, Jacqueline L. Doyle, Robert D. Hardie, George W. Logan, Wallace Stettinius

1st Edition

0300117094, 978-0300117097

More Books

Students also viewed these General Management questions

Question

describe several successful positive work interventions.

Answered: 1 week ago