Question

1 Approved Answer

The manager of a utility company in the Texas panhandle wants to develop quarterly forecasts of power loads for the next year. The power loads

The manager of a utility company in the Texas panhandle wants to develop quarterly forecasts of power loads for the next year. The power loads are seasonal, and the data on the quarterly loads in megawatts (MW) for the last four years are as follows:

Quarter Year 1 Year 2 Year 3 Year 4 1 103.2 98.1 123.5 107.8 2 126.9 118.6 154.2 130.2 3 149.2 140.3 168.2 147.6 4 164.1 153.1 179.4 169.0

The manager estimates the total demand for the next year at 652 MW. Use the multiplicative seasonal method to develop the forecast for each quarter. (Round all intermediate calculations to three decimal places.) The first quarter forecast is ______ MW. (Enter your response rounded to one decimal place.) The second quarter forecast is _______MW. (Enter your response rounded to one decimal place.) The third quarter forecast is _______ MW. (Enter your response rounded to one decimal place.) The fourth quarter forecast is ______ MW. (Enter your response rounded to one decimal place.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Financial Accounting

Authors: V.K. Gopal

1st Edition

9788174467461

More Books

Students also viewed these Accounting questions