The manager of the Personnel Department at City Enterprises has been reading about time-driven ABC and wants to apply it to her department. She has identified four basic activities her employees spend most of the their time on: Interviewing. Hiring, Assessment and Separation Processing. The department employs 8 staff who perform these activities. The manager provides the following estimates for the amount of time it takes to complete each of these activities: . . Interviewing: 95 minutes. Hiring: 85 minutes Assessment 125 minutes Separation Processing: 115 minutes. . Employees In Personnel work 34-hour weeks with four weeks for vacation of the 34 hours, five are reserved for administrative tasks. training, and so on. The costs of the Personnel Department, including any allocated costs from other staff functions, are $1.503,360. During the year, Personnel conducted 1.250 Interviews, made 400 hires, made 4,000 assessments, and had 350 separations The manager of the Personnel Department decides that her estimate of the activities might be too simple in two ways. First, the time to Interview depends on the level of the position for which a candidate is sought. She estimates that for a candidate at the manager level. the additional Interviewing time is 170 minutes. (Personnel Department employees only conduct the Initial Interview, but they accompany the candidate for Interviews by the hiring executive or CEO) For a candidate at the executive level, the additional time for Interviewing is 485 minutes (In addition to the time required for a manager The second issue she identified is that the time for separation processing depends on whether the separation is voluntary. She estimates that an involuntary separation requires an additional 305 minutes of personnel time. Required: a. What is the total time required for the Interviewing activity b. What is the total time required for the separation processing activity c. What is the cost of interviewing a manager? An executive? d. What is the cost of a voluntary separation? An Involuntary separation? a Complete this question by entering your answers in the tabs below. Required A Required B Required Required What is the total time required for the interviewing activity? Manager Executive minutes minutes The manager of the Personnel Department at City Enterprises has been reading about time-driven ABC and wants to apply it to her department. She has identified four basic activities her employees spend most of the their time on: Interviewing. Hiring, Assessment and Separation Processing. The department employs 8 staff who perform these activities. The manager provides the following estimates for the amount of time it takes to complete each of these activities: . . Interviewing: 95 minutes. Hiring: 85 minutes Assessment 125 minutes Separation Processing: 115 minutes. . Employees In Personnel work 34-hour weeks with four weeks for vacation of the 34 hours, five are reserved for administrative tasks. training, and so on. The costs of the Personnel Department, including any allocated costs from other staff functions, are $1.503,360. During the year, Personnel conducted 1.250 Interviews, made 400 hires, made 4,000 assessments, and had 350 separations The manager of the Personnel Department decides that her estimate of the activities might be too simple in two ways. First, the time to Interview depends on the level of the position for which a candidate is sought. She estimates that for a candidate at the manager level. the additional Interviewing time is 170 minutes. (Personnel Department employees only conduct the Initial Interview, but they accompany the candidate for Interviews by the hiring executive or CEO) For a candidate at the executive level, the additional time for Interviewing is 485 minutes (In addition to the time required for a manager The second issue she identified is that the time for separation processing depends on whether the separation is voluntary. She estimates that an involuntary separation requires an additional 305 minutes of personnel time. Required: a. What is the total time required for the Interviewing activity b. What is the total time required for the separation processing activity c. What is the cost of interviewing a manager? An executive? d. What is the cost of a voluntary separation? An Involuntary separation? a Complete this question by entering your answers in the tabs below. Required A Required B Required Required What is the total time required for the interviewing activity? Manager Executive minutes minutes