The managers of Merton Medical Clinic are analyzing a proposed project.The project's most likely NPV is $120,000,
Fantastic news! We've Found the answer you've been seeking!
Question:
The managers of Merton Medical Clinic are analyzing a proposed project.The project's most likely NPV is $120,000, but, as evidenced by the following NPV distribution, there is considerable risk involved:
ProbabilityNPV
0.05($700,000)
0.20(250,000)
0.50120,000
0.20200,000
0.05300,000
I need the project's expected NPV and standard deviation of NPV.