Question
The manufacturing company prepares the following budget for 2020. Machining Finishing Factory overhead $ 96,000 $ 200,000 Machine hours 6000 840 Direct labour cost $
The manufacturing company prepares the following budget for 2020.
Machining Finishing
Factory overhead $ 96,000 $ 200,000
Machine hours 6000 840
Direct labour cost $ 60,000 $ 400,000
This company uses a predetermined overhead rate for applying overhead based on machine hours for 'machining' and direct labour cost for 'finishing'.
You are given the following actual information about one job:
Machining Finishing
Direct materials used $ 11,000 $ 3,000
Machine hours 300 40
Direct labour cost $ 10,000 $ 20,000
Required:
(1) Compute the total cost (full cost) for this job.
(2) Why we need to develop Activity-based costing
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started