The marketing department at Bellevue University is working on a project with the following information. The Activity Time is also referred to as the Normal
The marketing department at Bellevue University is working on a project with the following information. The Activity Time is also referred to as the Normal Activity Time and is the time it takes to complete the activity based on the normal times. The Total Time After Crashing is the time it takes to complete the activity if this activity is crashed.
Activity | Immediate Predecessors | Activity Time (Days) | Activity Cost (Total) | Total Time After Crashing (Days) | Activity Crash Cost (Total) |
A | -- | 6 | $10,000 | 4 | $12,000 |
B | -- | 4 | $5,500 | 2 | $7,300 |
C | A, B | 3 | $6,000 | 2 | $7,500 |
D | C | 6 | $4,000 | 4 | $6,400 |
E | C | 4 | $3,500 | 2 | $5,100 |
a) What is the critical path for this project, what is the project completion time, how much total work time (in days) is required for this project, and what is the cost for completing this project using the Activity Time? Also identify the slack time for each path. The slack time for each path should be based on the time to complete the critical path.
b) Suppose that the school wants to complete the project in 12 days by crashing the most economical activity(ies). Which activity(ies) should it crash and how much will the project cost increase from your answer in a)?
c) Start with the original Activity Times in answering this part. In addition to the cost information provided above, indirect project costs total $500 per day. The company also incurs $400 in penalty costs for each day the project lasts beyond ten days. What is the minimum cost schedule for this project? What is the cost of this schedule and what is the project completion time?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started