The marketing department at Bellevue University is working on a project with the following information. The Activity Time is also referred to as the Normal

The marketing department at Bellevue University is working on a project with the following information. The Activity Time is also referred to as the Normal Activity Time and is the time it takes to complete the activity based on the normal times. The Total Time After Crashing is the time it takes to complete the activity if this activity is crashed.

Activity Immediate Predecessors Activity Time (Days) Activity Cost (Total) Total Time After Crashing (Days) Activity Crash Cost (Total)
A -- 6 $10,000 4 $12,000
B -- 4 $5,500 2 $7,300
C A, B 3 $6,000 2 $7,500
D C 6 $4,000 4 $6,400
E C 4 $3,500 2 $5,100

a) What is the critical path for this project, what is the project completion time, how much total work time (in days) is required for this project, and what is the cost for completing this project using the Activity Time? Also identify the slack time for each path. The slack time for each path should be based on the time to complete the critical path.

b) Suppose that the school wants to complete the project in 12 days by crashing the most economical activity(ies). Which activity(ies) should it crash and how much will the project cost increase from your answer in a)?

c) Start with the original Activity Times in answering this part. In addition to the cost information provided above, indirect project costs total $500 per day. The company also incurs $400 in penalty costs for each day the project lasts beyond ten days. What is the minimum cost schedule for this project? What is the cost of this schedule and what is the project completion time?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management

Authors: Richard L. Lynch

6th Edition

978-0273750925

More Books

Students also viewed these General Management questions