Question

1 Approved Answer

The metal parts to be used on the Echo assembly line were produced in an automated machining center on any one of six ( 6

The metal parts to be used on the Echo assembly line were produced in an automated
machining center on any one of six (6) identical machines. Each Echo fuel dispenser required eight
(8) machined parts. The machines were flexible so that any one of the six machines could work
on the parts as needed. The average production time per part was 12 minutes. Raw material before
the machining center consisted of parts waiting to be processed, and post-production work-inprocess was held in an inventory buffer. The machining stage worked on 1 batch of 40 dispensers
at a time. What is the capacity of this stage in dispensers per day?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Effective small business management An Entrepreneurial Approach

Authors: Norman M. Scarborough

10th Edition

132157462, 978-0132157469

More Books

Students also viewed these General Management questions