The modified ElfC ratio for a cityowned hospital heliport project is 1.7. The initial cost is $0.625 million, annual benefits are $150,000. and the estimated
The modified ElfC ratio for a cityowned hospital heliport project is 1.7. The initial cost is $0.625 million, annual benefits are $150,000. and the estimated life is 30 years. What is the amount of the annual M&O costs used in the calculation at a discount rate of 6% per year? The annual M&O costs is $ 42,829.72 0