The month of June just came to an end, which was the 7th month in a 19 month project with a BAC of $92M that
The month of June just came to an end, which was the 7th month in a 19 month project with a BAC of $92M that you are managing. You just received the following cumulative cost measurements: BCWS = $28M, BCWP = $51M; ACWP = $64M What is your SV? Note: M stands for Million. While giving your answers you do not need to write the units. For example; simply write 80.25 for $80.25M. Please keep two digits after decimal point if necessary