Question

1 Approved Answer

The official setup time for a machine is 4 0 minutes. Suppose a workday is 4 2 0 minutes, the machine must process 2 0

The official setup time for a machine is 40 minutes. Suppose a workday is 420 minutes, the
machine must process 200 parts a day, and the processing time is 0.5minunit.
a. What is the minimum batch size?
b. Suppose the operation is run for one day using the batch size from (a), and at the end of
the workday only 133 units have been produced. Assuming the processing time per unit
is 0.5 minutes, and no stoppages except for setup, how much time was used for setup?
What was the average time per setup? Explain how the actual setup time could be so
much longer than the official setup time.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Essentials of strategic management

Authors: Charles w. l. hill, Gareth r. Jones

3rd Edition

1111525196, 978-1111525194

More Books

Students also viewed these General Management questions

Question

Every non square system of linear equations has a unique solution.

Answered: 1 week ago