The official start day of the Project is Monday March 4 , 2 0 2 4 . You do not need to set a Baseline

The official start day of the Project is Monday March 4,2024. You do not need to set a Baseline for the Project. Please show on MS project. Activity Sequencing The following statements define the sequence of Activities/Tasks and their inter-relationships:
1. The first task in the plan is to acquire the Building Permit
2. Excavation of Foundation can begin immediately following the Building Permit has been acquired
3. Basement Construction and Installation of Underground Services commence as soon as Excavation
of Foundation is complete
4. Wood Framing begins as soon as Basement Construction is complete
5. Backfill Basement follows Basement Construction and Installation of Underground Services
6. Milestone: Foundations Completed is dependent on Backfill Basement
7. Roof Framing follows completion of Wood Framing
8. Exterior Brickwork can start when Roof Framing and the work package Foundations Completed is
completed
9. Metal Siding installation follows the completion of External Brickwork
10. Windows can be installed when Metal Siding is 50% complete
11. HVAC and Electrical Rough In, Plumbing Rough In and Roof Finish can all commence as soon as Roof
Framing is complete.
12. Milestone: Structure Completed is dependent on Windows and Roof Finish
13. Drywall commences when Roof Finish, Metal Siding and Windows are complete
14. Carpentry Finishes commences on the completion of Drywall installation
15. Millwork can start when Carpentry Finishes are two thirds complete
16. HVAC and Electrical Fittings can commence when HVAC and Electrical Rough In has been completed
and when two thirds of the Drywall task duration has elapsed
17. Plumbing Fittings commence when Plumbing Rough In and Drywall are complete
18. Milestone: Services Completed is dependent on Plumbing Fittings
19. Painting and Decoration can commence only when all of the following tasks have been completed:
Carpentry Finishes, Millwork, HVAC and Electrical Fittings, and Plumbing Fittings
20. Carpeting and Tiling commences when Painting and Decorating is complete
21. Milestone: Finishes Completed is dependent on Carpeting and Tiling
22. Lot Grading commences when Drywall installation is complete
23. Driveway is installed when Lot Grading is complete
24. Landscaping commences when Driveway is complete
25. Inspection and Hand Over takes place when both Carpeting and Tiling and Landscaping are
complete.
26. Milestone: Exterior Works Completed is dependent on Landscaping
27. Milestone: Inspection and Handover is your final milestone for this project. This milestone is
dependent on all of the work package milestones completing
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Social Media Measurement And Management

Authors: Jeremy Harris Lipschultz

1st Edition

0815363923, 978-0815363927

More Books

Students also viewed these General Management questions