The official start day of the Project is Monday March 4 , 2 0 2 4 . You do not need to set a Baseline
The official start day of the Project is Monday March You do not need to set a Baseline for the Project. Please show on MS project. Activity Sequencing The following statements define the sequence of ActivitiesTasks and their interrelationships:
The first task in the plan is to acquire the Building Permit
Excavation of Foundation can begin immediately following the Building Permit has been acquired
Basement Construction and Installation of Underground Services commence as soon as Excavation
of Foundation is complete
Wood Framing begins as soon as Basement Construction is complete
Backfill Basement follows Basement Construction and Installation of Underground Services
Milestone: Foundations Completed is dependent on Backfill Basement
Roof Framing follows completion of Wood Framing
Exterior Brickwork can start when Roof Framing and the work package Foundations Completed is
completed
Metal Siding installation follows the completion of External Brickwork
Windows can be installed when Metal Siding is complete
HVAC and Electrical Rough In Plumbing Rough In and Roof Finish can all commence as soon as Roof
Framing is complete.
Milestone: Structure Completed is dependent on Windows and Roof Finish
Drywall commences when Roof Finish, Metal Siding and Windows are complete
Carpentry Finishes commences on the completion of Drywall installation
Millwork can start when Carpentry Finishes are two thirds complete
HVAC and Electrical Fittings can commence when HVAC and Electrical Rough In has been completed
and when two thirds of the Drywall task duration has elapsed
Plumbing Fittings commence when Plumbing Rough In and Drywall are complete
Milestone: Services Completed is dependent on Plumbing Fittings
Painting and Decoration can commence only when all of the following tasks have been completed:
Carpentry Finishes, Millwork, HVAC and Electrical Fittings, and Plumbing Fittings
Carpeting and Tiling commences when Painting and Decorating is complete
Milestone: Finishes Completed is dependent on Carpeting and Tiling
Lot Grading commences when Drywall installation is complete
Driveway is installed when Lot Grading is complete
Landscaping commences when Driveway is complete
Inspection and Hand Over takes place when both Carpeting and Tiling and Landscaping are
complete.
Milestone: Exterior Works Completed is dependent on Landscaping
Milestone: Inspection and Handover is your final milestone for this project. This milestone is
dependent on all of the work package milestones completing
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started