Question

1 Approved Answer

The Oloibiri Field cost $640 million to develop, including all Exploration and Appraisal expenditure and pre-license costs. It is estimated that the field had, at

The Oloibiri Field cost $640 million to develop, including all Exploration and Appraisal expenditure and pre-license costs. It is estimated that the field had, at inception the following reserves:

- 240 million barrels of Proved Reserves

- 320 million barrels of Proved and Probable Reserves

- Production up to and including 31-12-2019 was 20 million barrels

Required:

  1. Calculate the DD&A rate per barrel on Unit of Production (UoP) basis. Use Proved Reserves as your reserve definition.
  2. Calculate the DD&A charge up to 31-12-2019.
  3. Calculate the DD&A rate per barrel on Unit of Production (UoP) basis. Use Proved plus Probable Reserves as your reserve definition.
  4. Calculate the DD&A charge up to 31-12-2020.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Contabilidad Para No Contadores

Authors: Wayne Label

2nd Edition

9587712986, 9789587712988

More Books

Students also viewed these Accounting questions

Question

Discuss the determinants of direct financial compensation.

Answered: 1 week ago