The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the makespan to complete

The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the makespan to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are as follows

What is the optimum sequence (first car to last)?

Car A B D E Body Work (hrs) 10 5 7 3 1 Paint (hrs) 2 4 5 6 7

Step by Step Solution

3.38 Rating (151 Votes )

There are 3 Steps involved in it

Step: 1

Using Johnsons rule we assign the item with smallest task body work from left to right at one e... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Statistics For Management And Economics Abbreviated

Authors: Gerald Keller

10th Edition

978-1-305-0821, 1285869648, 1-305-08219-2, 978-1285869643

More Books

Students also viewed these Mathematics questions

Question

Solve the following proportions for the unknown quantities

Answered: 1 week ago