The planning for a project determined it is composed of the following tasks, predecessors, and durations (note the two columns): TASK PREDECESSORS DURATION TASK PREDECESSORS
The planning for a project determined it is composed of the following tasks, predecessors, and durations (note the two columns):
TASK | PREDECESSORS | DURATION | TASK | PREDECESSORS | DURATION |
A | - | 6 | N | K | 9 |
B | - | 7 | O | L | 5 |
C | B | 5 | P | O | 7 |
D | A,C | 10 | Q | M | 20 |
E | D,I | 16 | R | M | 10 |
F | - | 9 | S | R | 12 |
G | F | 11 | T | R | 10 |
H | - | 10 | U | N,P,T | 8 |
I | G,H | 18 | V | U | 9 |
J | E | 8 | W | Q,S,V | 10 |
K | E | 5 | X | Q,S | 6 |
L | E | 8 | Y | X | 9 |
M | J | 8 | Z | Q | 5 |
Without using any software package, manually construct the appropriate CPM network diagram using theactivity on arrowconvention and the techniques discussed in the class. You must submit your diagram for full credit:
In an attached file, address the following:
(a)For each task, give the Earliest Start, Latest Start, Earliest Finish, Latest Finish, and Total Float.
(b)What sequence of tasks makes up the Critical Path? Include any dummy activities that may be a part of the critical path.
(c)What is the total duration of the project as planned?
CPM Table Template.xlsx
Activity Earliest Start Latest Start Earliest Finish Latest Finish Total Float B D H ZOO AV - > > B X N Sequence of tasks that make up the critical path: Total duration of the project as plannedStep by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started