The planning horizon is defined as the amount of time the master schedule record or MRP record extends into the future. Which of the following

The planning horizon is defined as the amount of time the master schedule record or MRP record extends into the future. Which of the following is true about the planning horizon?
The length of the planning horizon is always fixed, regardless of how long or short production and supplier lead times may be.
There is no relationship between the length of the planning horizon and the lengths of production and supplier lead times.
In general, the longer the production and supplier lead times, the longer the planning horizon must be.
In general, the longer the production and supplier lead times, the shorter the planning horizon must be.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: R. Dan Reid, Nada R. Sanders

4th edition

9780470556702, 470325046, 470556706, 978-0470325049

More Books

Students also viewed these General Management questions