The Polo Development Firm is building a shopping center. It has informed renters that their rental spaces will be ready to occupy in 18 months.
The Polo Development Firm is building a shopping center. It has informed renters that their rental spaces will be ready to occupy in 18 months. If the expected time until the shopping center is completed is estimated to be 15 months, with a standard deviation of 5 months, what is the probability that the renters will not be able to occupy in 18 months?