The precedence diagram of a project is provided as follows. All task dependencies are Finish-toStart and the time unit is in days. a. What is
The precedence diagram of a project is provided as follows. All task dependencies are Finish-toStart and the time unit is in days. a. What is the critical path of this project? b. What is the duration of this project? c. How many days can we delay activity D without affecting the project completion date? d. What will happen if we delay activity F by 4 days