Question
The process to build a special type of coffee table follows four steps, required to be performed in sequence. The steps, relevant production rates, and
The process to build a special type of coffee table follows four steps, required to be performed in sequence. The steps, relevant production rates, and number of workers available are as shown in the table below. Assume that workers are not shared between operations.
Operation
Production time or rate (per worker)
Workers Available
Cutting
2 tables per minute
1 worker
Sanding
12 minutes per table
2 workers
Assembly
3 tables per hour
3 workers
Finishing
8 tables per hour
2 workers
Assume that the bottleneck operation is identified and a worker is added to that operation. What will be the new capacity of the system (in tables/hour) after the additional worker is added to the bottleneck operation?
a.
9 tables/hour
b.
10 tables/hour
c.
12 tables/hour
d.
16 tables/hour
e.
More than 100 tables/hour
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started