the product backlog is prioritized by the _________, while the Sprint backlog is prioritized by the _________. Question 42Answer a. product owner, team b. project
the product backlog is prioritized by the _________, while the Sprint backlog is prioritized by the _________. Question 42Answer a. product owner, team b. project manager, product owner c. product owner, scrum master d. customer, scrum master e. scrum master, team