The production budget shows expected sales units are 440000 . The required production units are 449000 . What are the beginning and desired ending finished goods units, respectively? Beginning Units EndingUnits 140005000 500014000 900014000 140009000 Coronado Industries is planning to sell 1000 boxes of ceramic tile, with production estimated at 970 boxkes during Mary. Each box of tile requires 40 pounds of day mix and a 0.25 hour of direct labor. Clay mix costs $0.50 per pound and employees of the company are paid $15 per hour. Manufacturing overhead is applied at a rate of 110% of direct labor costs. Coronado has 3700 pounds of clay mix in beginning inventory and wants to have 4900 pounds in ending inventory. What is the total amount to be budgeted for direct labor for the month? $3750$14552$58208$3638 Oriole Company is planning to sell 900 boxes of ceramic tile, with production estimated at 720 boxes during May. Each box of tile requires 44 pounds of day mix and a 0.50 hour of direct labor. Clay mix costs $0.40 per pound and employees of the company are paid $15 per hour. Manufacturing overhead is applied at a rate of 110% of direct labor costs. Oriole has 3300 pounds of clay mix in beginning inventory and wants to have 5400 pounds in ending inventory. What is the total amount to be budgeted for manufacturing overhead for the month? $23760$29700$7425$5940 At January 1, 2022, Sheridan Company has beginning inventory of 2000 surfboards. Sheridan estimates it will sell 10000 units during the first quarter of 2022 with a 12% increase in sales each for the following quarters. Sheridan's policy is to maintain an ending finished goods inventory equal to 25% of the next quarter's sales. Each surfboard costs $100 and is sold for $175. What is the budgeted sales revenue for the third quarter of 2022 ? $2195200$2275000$525000$12544