The production machine works in a one shift, 1 7 1 6 hours a year. Planned maintenance shutdowns were 5 days ( 4 0 hours

The production machine works in a one shift, 1716 hours a year. Planned maintenance shutdowns were 5 days (40 hours) a year. The machine defect 70 hours / year.
Set ups and short stops took 150 hours / year.
The machine produces a one product at optimal conditions in two hours.
The machine produced 600 products per year. Quality losses were 30 products. What were the OEE factors? What was OEE-value?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Time Management

Authors: Patrick Forsyth

4th Edition

0749475811, 978-0749475819

More Books

Students also viewed these General Management questions