The production manager at the Knox Machine Company is preparing a priority schedule
for one of the fabrication shop. The production manager has heard about six dispatching
rules: (1) shortest operation next (SON),(2) earliest due date (EDD),(3) earliest operation
due date (EODD),(4) least order slack, (5) Least slack per operation, or (6) critical ratio
(CR). The current shop status of the company is given below.
Assume 0.5 day move and queue time for each remaining operation, and current time is 0.
Order
Number
Total Remaining
Manufacturing
Time
Time
Remaining
until Due Date
Current
Operation
Processing Time
# of operation
remaining
1151814
2172043
3131722
4141331
5101564
6161655
Using the six sequencing rules, compute the scheduling priority for each order given in the
table above.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Bears Of The World Ecology Conservation And Management

Authors: Vincenzo Penteriani, Mario Melletti

1st Edition

1108483526, 978-1108483520

More Books

Students also viewed these General Management questions