The production supervisor of the Machining Department for Niland Company agreed to the following monthly static budget for the upcoming year: Niland Company Machining Department Monthly Production Budget Wages $486,000 Utilities 37,000 Depreciation 62,000 Total $585,000 The actual amount spent and the actual units produced in the first three months in the Machining Department were as follows: Amount Spent Units Produced January $553,000 105,000 February 526,000 95,000 March 506,000 86,000 The Machining Department supervisor has been very pleased with this performance because actual expenditures for January-March have been less than the monthly static budget of $585,000. However, the plant manager believes that the budget should not remain fixed for every month but should "flex" or adjust to the volume of work that is produced in the Machining Department. Additional budget information for the Machining Department is as follows: Wages per hour $17.00 Ubility cost per direct labor hour $1.30 Check My Work Next 2 more Check My Work uses remaining Previous Calculator The Machining Department supervisor has been very pleased with this performance because actual expenditures for January-March have been less than the monthly static budget of $585,000. However, the plant manager believes that the budget should not remain fixed for every month but should "flex" or adjust to the volume of work that is produced in the Machining Department. Additional budget information for the Machining Department is as follows: Wages per hour $17.00 Utility cost per direct labor hour $1.30 Direct labor hours per unit 0.25 Planned monthly unit production 114,000 a. Prepare a flexible budget for thectual units produced for January, February, and March in the Machining Department. Assume that depreciation is a fixed cost. Enter all amounts as positive numbers. If required, use per unit amounts carried out to two decimal places. Niland Company-Machining Department Flexible Production Budget For the Three Months Ending March 31 January February March Units of production Wages Ubilities Depreciation Total b. Compare the flexible budget with the actual expenditures for the first three months. Next Previous Check My Work 2 more Check My Work uses remaining Email Instructor Submit Assianment for Grading Save and Exit January February March Units of production Wages Utilities Depreciation Total b. Compare the flexible budget with the actual expenditures for the first three months January March February Total flexible budget Actual cost Excess of actual cost over budget What does this comparison suggest? The Machining Department has performed better than originally thought. The department is spending more than would be expected