The project information for the custom order project of the Air Control Company is presented here. Draw a project network Page 1 9 8 for
The project information for the custom order project of the Air Control Company is presented here. Draw a project network Page for this project. Compute the early and late activity times and slack times. Identify the critical path.
tableIDDescription,Predecessor,TimeAOrder review,None,BOrder standard parts,ACProduce standard parts,ADDesign custom parts,AESoftware development,AFManufacture custom hardware,C DGAssemble,B FHTest,E G