The project is behind schedule, over budget and used all its cost reserves and the team does not want to go to management and ask
The project is behind schedule, over budget and used all its cost reserves and the team does not want to go to management and ask to extend the project end date. Which of the following schedule compression techniques should the project team use?
Fast Tracking
Reduce Scope
Adding Lags
Crashing